Thursday 18 June 2015

Slab Foundation

13-6-15

Conducted a site inspection today to see completed formwork and all steel reinforcement laid, couldn't really fault anything, it was all as specified and done well.

Got a variation cost letter today, looking at a $3000 (extra) bill for removal of excess fill - I was expecting about half that cost.



 16-6-15

Did another site visit today to see the slab poured and formwork stripped. Also got a letter from Allworth for first progress payment - they don't much around.